Letter from client to the Consultant:
Dear Mr. Joanne,
I would like to inform you that we do not wish to go ahead with the Mezzanine floor arrangement in the workshop project, as it involves municipality approvals and huge investments. We would like to hold the Mezzanine project until the current market condition comes up.
Hence, we would like to start the operation only with the existing arrangement (only ground floor), for which, we need to do the following works. Kindly invite the proposal and finalise as soon as possible in order to start our operations.
Works to be carried out:
1. Concrete floor in the back portion
2. Epoxy flooring in the back portion
3. Arrangements of two offices with gypsum partition with necessary lighting arrangements
4. Arrangement of compressor room
5. Pending electrical works.
Your immediate response in this matter would be gretaly appreciated,
Thanks and regards,
Anil Chandan
Client Representative
Dear Mr. Joanne,
I would like to inform you that we do not wish to go ahead with the Mezzanine floor arrangement in the workshop project, as it involves municipality approvals and huge investments. We would like to hold the Mezzanine project until the current market condition comes up.
Hence, we would like to start the operation only with the existing arrangement (only ground floor), for which, we need to do the following works. Kindly invite the proposal and finalise as soon as possible in order to start our operations.
Works to be carried out:
1. Concrete floor in the back portion
2. Epoxy flooring in the back portion
3. Arrangements of two offices with gypsum partition with necessary lighting arrangements
4. Arrangement of compressor room
5. Pending electrical works.
Your immediate response in this matter would be gretaly appreciated,
Thanks and regards,
Anil Chandan